Aviagen VetLab
- Location: Elkmont, AL
- Project Delivery Method: Design-Build-Finance
- Owner: Aviagen, Inc.
- Budget: $1.8 Million
- Square Footage: 14,700
- Start Date: September 2010
- Completion Date: March 2011
- Architect: Spirit Architecture Group LLC
- Civil Engineer: Pugh Wright & McAnally
- Structural Engineer: Brough & Stephens, Inc.
- Mechanical Engineer: DW Collier Engineering, Inc.
- Electrical Engineer: Spirit Architecture Group, LLC
- General Trades: Pearce Construction
- Sitework: Limestone Building Group
- Concrete: LB Concrete Finishing
- Wood Framing: Garcia’s Construction
- Millwork: Bath & Kitchen Shop
- Roofing: North Alabama Aluminum
- Insulation: Frake’s Foam
- Doors & Hardware: Morard & Company
- Storefront: Grant Glass
- Walls & Ceilings: D & D Drywall
- Painting: Jason Howard Painting
- Specialties: Section 10 International
- Mechanical: J&R Sheet Metal, Inc.
- Plumbing: Hearn Plumbing
- Electrical: R & S Electric Company, Inc.
- Fire Alarm: R & S Electric Company, Inc.